From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the Maxima Residence residential complex continues. According to the project manager, a typical floor has been completed in the first section, and assembly of prefab stairs and ventilation units has begun.

Construction Status Update:

– In the first section, a typical floor is completed, assembly of prefab stairs and ventilation units begins;

– In the second section, the grillwork has been completed, the waterproofing of its underground part and the arrangement of the vertical elements of the basement floor are in progress;

– At the same time, in the third section, the construction of the retaining wall on the side of the neighboring residential complex and the arrangement of the piling field are being carried out;

– In the parking lot (first seizure) – preparation for the installation of the floor slab — 2nd floor is in progress.