From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.
In the first section, the arrangement of the floor of the 10th floor is completed, and the erection of the vertical elements of the 11th floor begins. In parallel, the laying of external and internal walls continues. The installation of reinforced concrete monolithic stairs and ventilation blocks continues, and the tower crane is attached.
In the second section, the floor covering of the fifth floor is ready, preparations are underway for the start of masonry walls, and the installation of ventilation units and reinforced concrete monolithic stairs is being carried out in parallel.
In the parking lot, 50% of the piles for the second seizure were completed.
In the third section, the installation of all piles has been completed.
You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.