From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.

In the first section, the vertical monolithic elements of the 14th floor are being arranged. Preparations are also underway for the extension of the tower crane for the transition to higher floors. Construction of external and internal walls is ongoing, already completed on six residential floors. Installation of prefabricated reinforced concrete monolithic stairs and ventilation units continues.

In the second section, the arrangement of the vertical elements of the tenth floor is being carried out, the masonry of the walls on the residential floors continues, and the installation of ventilation units and reinforced concrete monolithic stairs continues.

In the third section, the piling field is completely completed.

In the parking lot, all the pilings for the parking lot have been completed, concrete preparations have been made for the installation of the last grab near the neighboring residential complex, and the reinforcement of the monolithic grillwork has begun.

You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.