From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.
In the first section, the laying of external and internal walls is in progress, it has already been practically completed on five residential floors. At the same time, the installation of vertical monolithic elements of the 13th floor is being carried out, and the installation of prefabricated reinforced concrete monolithic stairs and ventilation units continues.
Backfilling is completed.
In the third section, the piling field was completed.
You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.