From Bosphorus Development and RIEL Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues according to plan.
First section: Active façade works and glazing of the lower floors are ongoing — the installation of porcelain stoneware tiles is starting. The substructure for the future installation of ceramic granite is being installed, insulation is being mounted, and sealing works are being carried out on the lower floors, while sealing above the 16th floor has already been completed. Passenger elevator installation is in an active phase — the planned completion of installation works is scheduled for March 2026.
Parking: Active masonry works are ongoing in the underground parking area.
Section Two: Installation of window structures continues on the upper floors, and the building perimeter is being actively enclosed with glass. In parallel, the installation of engineering networks is underway. The final layer of roof insulation has been completed. Façade works have begun — bracket installation is in progress.
Section Three: Relocation of engineering networks from the construction footprint has been completed. Currently, the foundation for Tower Crane No. 3 is being constructed.
Maxima Residence Residential Complex, which Bosphorus Development, together with System Developer RIEL, is creating as a business-class project, is located in the heart of Pechersk at 30 Konovalets Street. This is life in the rhythm of the city, where you don’t have to choose between comfort and location. Everything that shapes daily convenience is nearby: work, education, leisure, favorite routes, and places of inspiration. This is a home for those who value their time, space, and a sense of confidence in every day.
For information on purchasing apartments in the Maxima Residence residential complex and updates on construction progress, you can always contact the company’s sales department. Contact details are available via the provided link.