From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the second section, the monolith of the first floor is arranged, the floor slab is being constructed, the installation of reinforced concrete monolithic stairs and the installation of ventilation units are in progress.

In the first section, the covering of the fifth floor has been completed, the vertical of the sixth floor is being poured, and in parallel, the arrangement of reinforced concrete monolithic stairs and the installation of ventilation units are being carried out. Preparations for the masonry of the walls have begun.

At the same time, the pile field is being built in the third section, the readiness is 40%. Specialists also installed a tower crane.

The construction of the sales office has been completed near the construction site.

You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.