From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.
In the first section, the external and internal walls of the tenth floor are being laid, the tower crane is being built in parallel, and the vertical monolithic elements of the 16th floor are being installed. In addition, the installation of prefabricated reinforced concrete stairs and ventilation units is in progress. Installation of window structures has begun.
In the second section, the vertical elements of the 11th floor are being arranged, and the walls on the residential floors are also being laid. Installation of ventilation units and reinforced concrete stairs is underway.
On the territory of the parking lot, work on the reinforcement of the last monolithic grid on the side of the neighboring residential complex is being completed.
You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.