From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.

In the first section, the vertical elements of the eighth floor are completed, the laying of external and internal walls has begun, the arrangement of reinforced concrete monolithic stairs and ventilation blocks continues.

In the second section, the construction of the third floor is in progress, the masonry of the walls in the basement is in progress, the installation of ventilation units and reinforced concrete monolithic stairs continues.

In the third section, the piling field was arranged.

In the parking lot, the monolith of the first parking lot of the first encroachment has been completed, and earthworks for the second encroachment are ongoing.

You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.