From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues.

In the second section, the construction of the walls on the 10th floor is underway, the installation of the vertical elements of the 15th floor is in progress, and the installation of ventilation units and reinforced concrete monolithic stairs is being carried out in parallel. In the first section, the vertical monolithic elements of the 20th floor have been completed, and the laying of external and internal walls continues. The builders are preparing for the final construction of the tower crane. At the same time, the delivery of window structures to the facility continues.

In the parking lot, the vertical elements of the 2nd floor from the side of the neighboring residential complex are being prepared.

You can always find out about the purchase of apartments in the Maxima Residence residential complex and the progress of the construction of the complex in the sales department of the company. Contacts are available at the link.