The progress of the construction of the Maxima Residence residential complex in April 2025: in the first section, the monolithic frame arrangement has been completed
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the first section, the monolithic frame has been completed, and the masonry of the external and internal walls is 75%. The installation of ventilation blocks and reinforced concrete stairs has been completed. Currently, preparatory […]
The progress of the construction of the Maxima Residence residential complex in March 2025: in the first sections, the refinement of monolithic structures is carried out
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the first section, monolithic structures are being installed on the 26th floor, in parallel, the installation of ventilation blocks and reinforced concrete monolithic stairs is underway. The masonry of external and internal walls is […]
Bosphorus Development – Official Partner of the First Annual Forbes Ukraine Conference 2025: The Foundation of Success
On April 10, 2025, the first annual Forbes Ukraine conference was held, where Bosphorus Development was an official partner. Leading representatives of the construction industry were invited to the conference: developers, architects, industrialists, financiers, as well as representatives of the public sector. In total, the event brought together more than 400 guests, included: – World-renowned […]
The progress of the construction of the Maxima Residence residential complex in February 2025: in the first section is in the process of building walls
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the first section, the masonry of the walls on the 17th, 18th and 19th floors continues, while work is underway to arrange monolithic structures on the 24th floor. Ventilation blocks are being installed and […]
Start of sales of parking spaces in the residential complex Maxima Residence
The business class residential complex Maxima Residence in Pechersk has started selling parking lots! Now apartment owners can take care of the comfort and safety of their cars by having their own parking space in the heart of the city. Why is it beneficial? Comfort and security: a modern parking lot with a well-thought-out access […]
The progress of the construction of the Maxima Residence residential complex in January 2025: in the first section, monolithic structures on the 23rd floor are under construction
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the first section, monolithic structures are being installed on the 23rd floor, while the laying of external and internal walls continues from the 15th to the 18th floor. In the second section, the vertical […]
The progress of the construction of the Maxima Residence residential complex in December 2024: in the first section, the laying of external and internal walls is in progress
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. At the moment, the laying of external and internal walls continues in the first section. Work has been completed from the second to the ninth floor, and the 14th and 15th floors have now been […]
At the end of 2024, we at Bosphorus Development would like to share with you our results and achievements
Results of the Bosphorus Development year: together to the goal, despite the challenges. The year 2024 became a real challange for each of us. It was a time when Ukraine once again proved its strength, unity and indomitability. Bosphorus Development, despite all the difficulties, mobilized its resources to continue its contribution to the country’s development […]
The progress of the construction of the Maxima Residence residential complex in November 2024: in the first section, the arrangement of the vertical monolithic elements of the 18th floor is in progress
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. At the moment, in the first section, the monolithic framework is being completed, and the external and internal walls are being laid. In the second section, the arrangement of the vertical elements of the 18th […]
The progress of the construction of the Maxima Residence residential complex in October 2024: in the first section, the arrangement of the vertical monolithic elements of the 18th floor is in progress
From Bosphorus Development and Riel Real Estate Corporation we report that the construction of the residential complex Maxima Residence continues. In the second section, the construction of the walls on the 10th floor is underway, the installation of the vertical elements of the 15th floor is in progress, and the installation of ventilation units and […]