Construction of Maxima Residence, a business-class residential complex jointly developed by Bosphorus Development and System Developer RIEL is progressing according to schedule.
In the first section, installation of window units, window reveals, and drainage systems is 95% complete. Active work on updating the facade is underway. Installation of apartment entrance doors is 95% complete, while installation of doors to technical rooms is in progress. The substructure for HPL panels has been installed across 70% of the residential floor area. Screed installation and floor tiling have been completed on 20 floors of the section. Installation of engineering systems is 90% complete, and installation of the individual heating substation has commenced.
In the second section, installation of window units, window reveals, and drainage systems for the outdoor air-conditioning units is ongoing. Installation of engineering systems continues, while installation of the boiler room equipment has been completed. Screed installation is 80% complete. Façade works and installation of apartment entrance doors are also ongoing. In the area where Crane No. 1 was previously dismantled, foundation works for the central entrance group are underway.
In the third section, monolithic concrete works on the first floor have been completed. Construction of the monolithic structural frame for the typical floors is now commencing.
For information on purchasing apartments in the Maxima Residence residential complex and updates on construction progress, you can always contact the company’s sales department. Contact details are available via the provided link.