The construction of the business-class residential complex Maxima Residence, which is being implemented by the development companies Bosphorus Development together with System Developer RIEL, is progressing according to schedule.

In the first section, installation of window structures is nearing completion. Façade cladding with porcelain stoneware tiles is ongoing, while fire barriers have been installed on all window structures. The installation of window reveals and the drainage system is nearing completion.

In the second section, installation of window structures is ongoing, along with the installation of window reveals and the drainage system for external air-conditioning units. Installation of engineering systems is in progress. The boiler room equipment is 95% installed. Screed works are 75% complete. Façade works and the installation of apartment entrance doors are continuing. Crane №1 has been dismantled, and works on completing the podium structure are commencing.

In the third section, the reinforced concrete structure of the basement and ground floors has been completed. Construction of the reinforced concrete structure of the first floor is currently underway. Waterproofing of the foundation and basement walls has been completed.

For information on purchasing apartments in the Maxima Residence residential complex and updates on construction progress, you can always contact the company’s sales department. Contact details are available via the provided link.